摘要
介绍了北京地铁五号线崇文门车站近距离下穿既有线的设计施工技术措施,采用柱洞法施工工法和大管棚、联合注浆以及远程自动化监测等设计措施,保证了既有线变形在控制标准之内,为类似工程的设计施工提供了一定的经验和思路。
The design and construction mvasures tot Congwenmon statxon pass through the existing subway nearly was presented in this paper. The deformation of existing subway was under the control standard with column-cavity method and large tube shed, grouting, long-distance monitor etc, which provided some experiences and thoughts for the similar project.
出处
《工程质量》
2006年第6期27-30,33,共5页
Construction Quality
关键词
下穿
地铁既有线
设计
施工
pass through, existing subway, design, construction