摘要
分析了蚌埠地区拟建天然气热电联产系统在采暖运行中的困难,以及调峰运行方式的提出和参加电力调峰的途径等问题,并对热电联产系统的3种运行工况的特点、机组运行的要求、发电效率的影响等进行了探讨.
The paper analyzes the difficulties in heating operation of the planned heath-power combined production in the City of Bengbu, proposing the way of peak-gap operation, and way of joining the peak-gap system. Such problems as the characteristics of three operational conditions of heat-power combined production, the requirements of generation units, as well as effect on production efficiency, are also explored.
出处
《上海电力学院学报》
CAS
2006年第1期33-35,47,共4页
Journal of Shanghai University of Electric Power
关键词
热电联产
凋峰运行
燃气锅炉
蓄热罐
heat-power combined production
peak-gap operation
gas boiler
heat tank