简要介绍了鞍山市寰球大酒店和鞍山建设银行工程采用的多项施工新技术,主要有补偿收缩混凝土在箱基中的应用;外墙爬模、爬架;电梯井采用的弹性筒模;楼板支模早拆体系;混凝土布料机等.
The paper simply presents multinomial new construction technology adopted in the engineering projects of Anshan Global Hotel and Construction Bank by our corp.The content of the text mainly includes the application of compensation shrinkage concrete in the box foundation,climbing formwork and climbing frame applied in the construction of external-walls,elastic drum formwork used in the condruction of electrical lift well,floor supporting formwork early dismantling system.concrete distributing device,etc.
出处
《工业建筑》
CSCD
北大核心
1996年第8期38-40,50,共4页
Industrial Construction
关键词
高层建筑
施工工艺
补偿收缩
膨胀率
compensation-shrinkage
expensive-rate
crack
climbing-formwork
climbing-frame