超临界锅炉不熄火降压法蒸汽吹洗 被引量:5

STEAM BLOWING FOR SUPERCRITICAL PRESSURE BOILERS BY USING PRESSURE-REDUCING METHOD
下载PDF
导出
摘要 叙述华能沁北电厂一期工程2×600MW国产化超临界机组锅炉起动调试采用不熄火降压法吹管的情况。实践证明,采用该方法时水冷壁水动力工况稳定,水冷壁、过热器以及再热器管壁不超温,运行人员操作的复杂程度大大简化。其成功应用可为类似水冷壁结构及起动系统直流锅炉蒸汽冲洗提供参考。 The situation of adopting pressurereducing method without flameout to blow tubes in commission debugging of boilers for homemade 2×600 MW supercritical units in the first project period of Huaneng Qinbei Power Plant has been presented. The practice proved that the adoption of said method makes the hydrodynamic performance in waterwall to be stable, and the tube wall of waterwall, superheater, and reheater to be not overtemperature, and the operating complexity of operators to be greatly simplified. The successful appication of said method can provide reference for steam blowing of oncethrough boilers with similar waterwall structure and similar startup system.
出处 《热力发电》 CAS 北大核心 2005年第12期66-67,共2页 Thermal Power Generation
关键词 600MW机组 超临界锅炉 蒸汽吹洗 吹管 水冷壁 600 MW unit supercritical boiler steam blowing steampipeline blowing waterwall
  • 相关文献

同被引文献19

引证文献5

二级引证文献21

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部