摘要
对福清垃圾电厂接入电网的各种方案进行技术经济比较,确定最优系统接入方案———机组以较低电压等级(10 kV)经3回线路接入系统,解决了电厂接入系统时线路电压损耗大、功率送出难的问题。通过电气计算,验证了所提方案的合理性。
This paper compares the technology and economy for various connecting schemes of Fuqing garbage incineration power plant to power grid,and chooses the optimal one:the units connect to grid through three loops under lower voltage level(10kV),to solve the problems of voltage loss and power transmission.The electrical calculation indicates that the proposed scheme is reasonable.
出处
《电力与电工》
2011年第4期22-24,共3页
Electric Power and Electrical Engineering
关键词
垃圾电厂
接入电网方案
技术经济比较
电源送出
电气校核
garbage incineration power plant
connected to power grid
technology and economy comparison
scheme of power sent out
electric check