阐述了江苏镇江电厂2台600MW机组工程循环水泵房沉井下沉过程中的稳定分析、纠偏控制以及对工程桩的保护措施,并对软土地基条件下沉井下沉须注意的问题提出处理建议。
The stability analysis, error correction control and project pile protection of the process of circulation water pump house well sinking in the project of two 600 MW units at Jiangsu Zhenjiang Power Plant is introduced, and the suggestion to deal with the problems of well sinking under the condition of soft soil foundation is provided.
出处
《江苏电机工程》
2005年第4期25-27,共3页
Jiangsu Electrical Engineering