红石岩水电站工程动床模型试验研究 被引量:5

Test study on the movable-bed model for Hongshiyan Hydropower Station
下载PDF
导出
摘要 待建的红石岩水电站水库属严重淤沙型水库,通过动床水工模型试验和有关研究分析发现,其冲沙闸排沙效果不理想,引水隧洞存在进沙严重的隐患。为此,提出了增设一道导墙的方案,以减少引水隧洞进沙并提高冲沙闸排沙效果。同时,从提高电站的经济效益考虑,对运行方式提出了建议。 Based on the moveable-bed model tests and some relative studies, it is found that the proposal reservoir for the Hongshiyan Hydropower Station will be a heavy deposit reservoir, its sand-flushing sluice could not effectively de-silt and serious hidden-troubles exist in its diversion tunnel. For this reason, this paper puts forward a guide wall should be increased to reduce the sand flowing into the tunnel and increase sand-flushing effectiveness of sand gate. In addition, several operation suggestions have also been advised to enhance economic benefits of the hydropower station.
出处 《水力发电》 北大核心 2005年第6期27-28,44,共3页 Water Power
关键词 导墙 导沙坎 冲沙闸 动床模型试验 红石岩水电站 guide wall guide sand sill sand gate moveable-bed model test Hongshiyan Hydropower Station
  • 相关文献

参考文献5

  • 1惠遇甲,王桂仙编..河工模型试验[M].北京:中国水利水电出版社,1999:147.
  • 2吴持恭.水力学[M].北京:高等教育出版社,1982.. 被引量:78
  • 3谢鉴衡等编著..河床演变及整治[M].北京:水利电力出版社,1990:315.
  • 4钦荣著.河流推移质运动理论及其应用[M].北京:中国铁道出版社,1996.. 被引量:1
  • 5于鲁田主编..多沙水流泵站技术[M].北京:中国水利水电出版社,1999:178.

共引文献77

同被引文献21

引证文献5

二级引证文献26

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部