摘要
结合二滩水电站建设的实例,论述了一般土木工程施工合同中变更的依据、步骤等,对土木工程的设计和工程监理提出了一些建议。
In the light of practice in Ertar Hydropower Project,the basis steps for change in normal civil engi-neering construction contract are discussed. Some suggestions are proposed for civil engineering design andengmeermg supervisiong.
出处
《四川水力发电》
1994年第A00期72-76,共5页
Sichuan Hydropower
关键词
土木工程
工程施工
合同
工程承包
水电站
civil engineering change in construction contract project contract