摘要
为解决慈溪市域范围1市17镇的污水出路问题,在慈溪市污水治理一期工程中拟采用区域排水系统方式。通过对区域排水系统的总体布置、二级处理和深度处理的技术经济分析,最终确定区域排水系统采用三大污水收集系统、三座污水处理厂、分点进水倒置A/A/O脱氮除磷工艺以及人工湿地深度处理工艺的方案。
The regional sewerage system will be adopted in the first phase of Cixi wastewater treatment project, in order to solve the outlet of wastewater in urban area. By making general layout for the system and making techno-economic analysis on the secondary and advanced treatment, the following scheme shall be adopted:three sewage collection systems, three wastewater treatment plants, inverted A/A/O process with step feed for nitrogen and phosphorus removal, and constructed wetland for advanced treatment.
出处
《中国给水排水》
CAS
CSCD
北大核心
2005年第7期61-64,共4页
China Water & Wastewater
基金
科技部中法研究协作计划资助项目(P2R0301)
关键词
区域排水系统
污水收集系统
倒置A/A/O工艺
人工湿地
regional sewerage system
sewage collection system
inverted A/A/O process
constructed wetland