针对陕西华电蒲城发电有限责任公司一期2台机组DCS系统的操作和维护,分析了Foxboro公司的I/ASeries系列控制系统在使用和维护中常见的问题并提出了解决办法,对其它火电厂使用和维护分散控制系统有借鉴作用。
In the light of operation and maintenance of DCS system in Pucheng Power Generation Corporation Ltd. Phase I with capacity of 2 sets of 300MW unit, the common problems in the operation and maintenance of I/A Series control system by Foxboro Company are analyzed and relevant solutions are put forward. It can be used as reference for the other thermal power plant