摘要
本文介绍了水电站主厂房安装场平面尺寸的确定;分析和总结了葛洲坝等电站大型机组安装、检修的主要经验和特点;提出了多机组、大容量水电站设置两个安装场并充分利用安装场地,实现2台机组同时、平行、连续作业的可能性、必要性和应具备的必要条件,以及由于机组安装、检修工期缩短所产生的经济效益与社会效益。
The plan size determination of mounting ground for machine hall is introduced. The big set installation, the main overhaul experiences and features for Gezhouba Hydroelectric Plant, etc. are analysed and summed up. It is suggested that the two mounting grounds are set up for multi—set, big capacity hydroelectric plant and they are fully used to realize possibility, necessity and prerequisity for simultaneous, parallel, continuous operation of two sets, as well as the economic and social benefits gained due to set mounting and shortening the overhaul period.
出处
《水电站设计》
1993年第2期53-60,共8页
Design of Hydroelectric Power Station
关键词
机组
安装
水电站
水轮发电机
hydroelectric plant, turbo-generator set installation, overhaul, machine hall, mounting ground, simultaneous, parallel and continuous operation.