摘要
青印溪二级水电站用爆破膜代替调压井。进行了现场甩负荷试验,实测了蜗壳压力、机组转速升高、导叶开度的变化过程,分析了爆破膜的工作特性。
Safety membranes were used at Qingyinxi No.2 water power station in lieu of surge chamber. Field tests were carried out and the pressure rise, speed rise and the turbine gate opening were measured during load rejections. The Characteristics of safety membranes is analysed.
出处
《大电机技术》
北大核心
2005年第1期49-52,共4页
Large Electric Machine and Hydraulic Turbine