摘要
利用平面二维恒定流悬沙输运数学模型,模拟计算广东省惠州市境内东江干流博罗浅滩整治过程中,疏浚和抛泥对右岸义和自来水厂取水口的影响。定量地估算出施工期间义和水厂取水口处水质超标的时间和程度,为制定水环境保护对策措施提供依据。
we calculated effect of dredging up and mud discarding to water catchement in water way dredging project of BoLuo bank of DonJiang river in HuiZhou city, Guang Dong Province with plan two demension suspend sard transfer and diffuse model. we estimated period and degree of water quality beyond the limit at the water catchment and provide basis for establishing protection measwes of water environment.