介绍近距双洞隧道浅埋暗挖采用CRD法施工中利用各种辅助措施在粉砂地层中穿越铁路的施工经验。
In this article, the author introduces some experiences of the construction of a short-range shallow buried covered excavation tunnel which was built in silt stratum with the CRD construction method and others assistant measures to cross a railway.
出处
《施工技术》
CAS
北大核心
2004年第10期21-22,47,共3页
Construction Technology
关键词
浅埋暗挖
隧道
CRD法
粉砂地层
施工措施
shallow buried covered excavation
tunnel
CRD construction method
sandy silt soil stratum
construction measure