摘要
阐述了现场施工条件下的焊接施工工艺规范。探讨了CASE2199(T23)钢的焊接技术和焊接工艺规范,对焊接接头进行了各项性能试验,并取得了良好的试验效果。该焊接工艺已成功地应用于河津发电厂2×350MW机组工程的焊接。
This article illuminates the welding technics on the spot of construction,discuccess welding technology and technics of CASE2199.The experiments for welding joint s have been done and the results are satisfied applied in unit Hejin2×350MW power plant .
出处
《电焊机》
2003年第10期44-45,共2页
Electric Welding Machine