摘要
在地下室防水施工中,当采用土钉支护直接做地下室外墙外模时,如能合理地选用防水卷材,科学组织施工,可以减少土方挖填,少占施工用地,节省支模用工量,从而达到提前工期,降低工程成本的目的.该施工方法尤其适用于施工现场狭小,工期紧张条件下的工程.
In waterproof construction underground,when soil nail supportment is made as form of external wall of basement, it can decrease earthwork, save formwork andcost if reasonably selected materials and scientifically orgnised construction, especially on condition of construction space is limited or time limit for a project is not e-nough.
出处
《吉林建筑工程学院学报》
CAS
2003年第4期18-20,29,共4页
Journal of Jilin Architectural and Civil Engineering
关键词
土钉支护
外墙
外模
地下防水
soil nail support
external wall
external form
waterproof of basement