摘要
通过对 3m× 6m(高×宽 )连杆滚轮式水力自控翻板闸门的水力学试验研究 ,优化出闸门运行稳定最佳设计后支承点位置 ,并且将试验成果应用于实际工程中 ,取得了较好效果。
Through hydraulics experiment study on the hydraulic automatic control oscillating flashboard of 3 m×6 m with connecting rod and idler wheel, the back fulcrum of the flashboard optimal design under steady operation is found. Through application of the experiment results in actual work, good effects are obtained. The study results can provide reference for the flashboard design of the same type and the same sizes.
出处
《中国农村水利水电》
北大核心
2004年第10期47-49,共3页
China Rural Water and Hydropower
关键词
水力自控翻板闸门
支点
运行稳定
hydraulic automatic control oscillating flashboard
fulcrum
steady operation