摘要
对广东汕头电厂(2×300MW+1×600MW)、台山发电厂(8×600MW)、珠海发电厂(2×660MW+4×660MW)大型火力发电厂的灰堤、护岸、防波堤等筑堤工程几个不同建设方案的优缺点进行比较分析,最终选择水下爆炸处理软基筑堤法的方案。采用该方法,施工简便,建设工期短,地基稳定,造价低,社会效益和经济效益显著。
The different schemes for constructing the ash dump dike,bank revetment and seawall of Shantou Power Plant (2×300 MW+1×600 MW),Taishan Power Plant (8×600 MW) and Zhuhai Power Station (2×660 MW+4×660 MW) in Guangdong Province are analyzed and compared, and the diking method with underwater burst treated soft base is selected. This method is of simple and convenient procedures, short construction period, stable foundation and low costs, and can bring about prominent social and economic benefits.
出处
《广东电力》
2004年第4期56-58,共3页
Guangdong Electric Power
关键词
大型火电厂
海堤
水下爆炸
软基
large thermal power plant
seawall
underwater explosion
soft base