宁波联盛高空钢结构连廊液压同步整体提升施工分析 被引量:7

Construction of hydraulic synchronizing integral lifting in high steel sky-bridge at Ningbo Liansheng
原文传递
导出
摘要 宁波联盛钢结构连廊工程,由于施工高度高、构件重量较大以及施工场地限制等原因,常规起重设备吊装施工难度大,高空原位散拼及其他方法都无法实施。通过多方案比选,连廊两端钢骨柱采用人字抬灵式桅杆起重机安装,连廊桁架在五层楼面拼装,采用液压同步整体提升的施工方案。此方法克服了狭小场地高空重型钢结构的施工困难,实际的施工结果与方案的方法、验算吻合,效果显著。对施工过程进行非线性有限元分析,实际施工监测与分析结果吻合。对复杂连接节点做了有限元分析,并根据计算结果对节点构造设计进行了完善。本施工方法对类似项目的实施具有较好的参考价值。 The steel sky-bridge of Ningbo Liansheng square,because of Long-span and heavy weight,is difficult for constructing in normal method,such as assembling in suit at high altitude. Through comparison and selection of different plans,the technology of hydraulic synchronizing integral lifting of the sky-bridge was selected,and the columns were erected by mast crane. The construction sequence is the truss of the sky-bridge,which were assembled on fifth floor. This technology breaks the normal methods that construction in sequence from lower to upper. The finally construction verified this method actually. Non-liner FEM analysis was used in construction process,which was anastomosed to measurement results. The joints are optimized by the results of FEM analysis. The construction method has a good reference value to similar projects.
出处 《建筑结构》 CSCD 北大核心 2013年第S1期1012-1016,共5页 Building Structure
关键词 大跨重型 高空 钢结构连廊 液压同步 整体提升 long-span and heavy high altitude steel sky-bridge hydraulic synchronizing integral lifting
  • 相关文献

参考文献1

二级参考文献2

  • 1冶金工业部建筑研究总院.钢结构工程施工质量验收规范[S]北京:中国计划出版社,2002. 被引量:1
  • 2中冶集团建筑研究总院.建筑钢结构焊接技术规程[S]北京:中国建筑工业出版社,2003. 被引量:1

共引文献7

同被引文献44

引证文献7

二级引证文献37

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部