通过对山西省某500 kV变电工程的决(结)算、批复概算与通用造价的对比分析,总结了变电工程造价管理的经验与存在的问题,对各等级变电工程建设造价管理具有可以借鉴的作用。
Sum up the experiences and existing problems of substation project building cost control management by contrasting and analyzing the final accounts,the settle accounts,the approved budget and general cost of a 500 kV substation project in Shanxi province.This research can be used for reference to all grades of substation project building cost control.
出处
《电力学报》
2012年第6期627-630,共4页
Journal of Electric Power
关键词
电力建设
变电工程
造价
概算
结算
electric power construction
substation project
cost
budget
settle accounts