反井钻机开挖导井(3.5m)补充定额编制研究 被引量:5

Research on the Compilation of Supplementary Quota of Raise-boring Machine in Construction of Pilot Shaft(3.5m)
下载PDF
导出
摘要 反井钻机开挖导井朝着大直径工艺发展,而水电行业现有相关定额中无反井钻机开挖大直径导井(孔径>2.0m)相关定额。对白鹤滩水电站导井开挖过程中统计的实测资料进行整理、计算分析,编制反井钻机开挖3.5m导井补充定额。与有色金属工业预算定额、类似工程实施价对比,结果表明补充定额编制合理,可为类似工程的单价编制、成本控制等提供参考。 The pilot shaft excavation with raise boring machine is developing towards large diameter technology,but there is no relevant quota for large diameter pilot shaft(D>2.0 m)excavation in the existing relevant quota of hydropower industry.This paper analyzes and calculates the measured data of pilot shaft excavation in baihetan hydropower station,and makes out the supplementary quota of 3.5m pilot shaft excavation with raise boring machine.Compared with the other quota and implementation price,the results show that the supplementary quota is reasonable,which can provide reference for price compilation and cost control of similar projects.
作者 华攸和 苏锦鹏 范宏伟 徐旭敏 HUA Youhe;SU Jinpeng;FAN Hongwei;XU Xumin(Power China Huadong Engineering Corporation Limited,Hangzhou,311122,China;China Three Gorges Construction Management Co.,Ltd,Chengdu 610000,China)
出处 《建筑经济》 北大核心 2021年第S01期66-70,共5页 Construction Economy
关键词 反井钻机 水电工程 3.5m导井 补充定额 raise boring machine hydropower projects 3.5m pilot shaft supplementary quota
  • 相关文献

参考文献5

二级参考文献28

共引文献16

同被引文献24

引证文献5

二级引证文献2

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部