摘要
结合实际工程应用,介绍了在填海造地地区根据火力发电厂各建筑物使用要求不同,分别采用强夯、预应力钢筋混凝土管桩和振冲碎石桩对厂区地基进行联合处理的经验及相关试验结论,对各种处理方法的施工参数、检测手段等提出建议,为类似场地工程地基处理提供参考。
Based on practical engineering application, the paper introduces the experiences and relevant test results of combined treatment, including dynamic compaction, pre-stressed concrete pipe pile and vibro-replacement stone column, of the hydraulic sand fill site on seashore for thermal power plant, according to different requirements of various buildings of the thermal power plant. Suggestions are proposed on construction parameter and testing method of various treatment methods, which can provide a reference for similar projects.
出处
《电力建设》
2011年第3期92-95,共4页
Electric Power Construction
关键词
火力发电厂
吹填砂
地基处理
强夯法
预应力高强混凝土管桩(PHC桩)
振冲碎石桩
thermal power plant
hydraulic sand fill
ground treatment
dynamic compaction
pre-stressed high-strength concrete pipe pile
vibro-replacement stone pile