摘要
通过介绍松散堆积体预应力锚索工程钻孔施工措施,阐述了施工过程中应注意的几个问题,并提供了部分施工参数,供从事类似工程施工的工程技术人员参考。
The construction measures of hole drilling of prestressed cable in loose deposit is introduced,some problems during construction should be paid attention,then some construction parameters are provided,which is taken as preferences for technicians.
出处
《土工基础》
2009年第1期16-18,共3页
Soil Engineering and Foundation
关键词
松散堆积体
预应力锚索
跟管套管
loose deposit
prestressed cable
coring with casing