摘要 介绍了用于快中子临界装置堆厅且不截断电缆的电气贯穿件,该贯穿件结构简单,便于电缆更换。贯穿件气密性试验和堆厅整体密封包容性试验结果表明,电气贯穿件的气密性优于设计指标,且使得堆厅整体密封包容性满足快中子临界装置正常运行和事故情况下的使用需求。 A electrical penetration assembly which does not require to cut cables and can be used in the hall for the fast critical assembly is introduced in this paper. The structure of the electrical penetration assembly is simple and facilitates the cable replacement. The results from the leakage test on the electrical penetration assembly and the hall indicate that the leakage ratio is less than the design ratio, and the overall seal performance of the hall satisfies the requirement on the normal operation and accident conditions for the fast critical assembly.
出处 《核动力工程》 EI CAS CSCD 北大核心 2008年第5期107-108,113,共3页 Nuclear Power Engineering
关键词 快中子临界装置 电气贯穿件 屏蔽 泄漏率 Fast critical assembly, Electrical penetration assembly, Shielding, Leakage ratio
  • 相关文献

参考文献3

二级参考文献6

  • 1姚梅生,吴莘馨,翁锡镅,博金海,刘志勇,李军,何学东.氦气试验回路中的氦净化[J].核动力工程,1995,16(5):470-475. 被引量:7
  • 2GB13538-92.核电厂安全电气贯穿件.[S].,.. 被引量:1
  • 3IEEE 317-1983. IEEE Standard for Electric Penetration Assemblies in Containment Structure for Nuclear Power Generating Stations. 被引量:1
  • 4Bump T R, Seidensticker R W, Shackelford M H. ANL survey of LWR containment penetrations: a progress report. Nuclear Engineering and Dedsign, 1985,90(2) : 167. 被引量:1
  • 5GB13538.核电厂安全壳电气贯穿件[S].1992. 被引量:1
  • 6ASME.锅炉及压力容器规范[S].第5卷,A分卷.2004. 被引量:1